GuessWho Wrote:
-------------------------------------------------------
> Gazza Wrote:
> --------------------------------------------------
> -----
> > same as was posted earlier - its quite
> confusing,
> > because in the next paragraph it only
> mentions 4
> > shows in June as being cancelled
> >
> > maybe its because theyre the only ones that
> have
> > been CONFIRMED as having been cancelled, I
> suppose
>
>
> The BBC updated their info........the original
> link didn`t mention the 2007 date for completion.
>
>
Indeed. They're still mentioning Bon Jovi as maybe going to Twickenham though - when its been confirmed officially that its Milton Keynes
However, Sky News interactive just now have mentioned that Multiplex have just released a statement saying the handover date will be June. If thats the case, then the Stones shows will probably be OK
This is the statement taken from Multiplex's own official website :
-----------------------------------------------------------------------------
Wembley Update
31st March 2006
In relation to the Wembley National Stadium project, Multiplex advises as follows:
Substantial completion of Contractor’s works is now anticipated by the end of June 2006 (previously May 2006), based upon a review of the costs and benefits of any acceleration measures. Previous updates relating to programme have presumed an integrated approach with Client’s works being completed simultaneously. Multiplex yesterday received advice from the client that it is now reconsidering whether it will or is able to continue to integrate its works, or whether it will commence these works post completion. Multiplex’s client, Wembley National Stadium Limited, is solely responsible for determining when it starts and completes its works and also when and which events are hosted at the stadium.
Substantial completion by the end of June will have certain works and certain activities such as commissioning and cleaning still to be completed after this date (refer to earlier releases).
Additional Wembley allowances were included in the Group’s latest interim results specifically to cover any further unforeseen delays. Based upon the programme noted above, no further adjustments to the project’s financial position are anticipated.
Multiplex has formally advised its client that Multiplex is entitled to substantial and legitimate extensions of time under the terms of its construction contract which will extend the contract completion date until at least September 2006. Not withstanding that it is Multiplex’s belief that it has until at least September to complete, Multiplex is targeting substantial completion by end of June as noted above.
In the last month Multiplex has achieved the following in relation to the structure:
�� Final de-prop of the roof
�� Erection of the remaining moving roof panels
�� Removal of five temporary trusses and three roof towers
�� Demobilisation of seven cranes
�� Handed over up to 60% of the roof for final roof sheeting �� Completed the south moving roof panel ready for commissioning
�� Completed 50% of the pitch ready for top soil and grass
The rafter incident in the northern roof, which was reported on 21st March 2006, involved the evacuation of site as a prudent safety measure as Multiplex took steps to ensure the rafter was secured in a controlled environment. The rafter is now being reinstated to its final position, where it will be assessed along with the surrounding elements for any further rectification work. The forecast impact affects the temporary works removal and associated works within the arena. The effects on the arena spread to the completion of the main service road at Basement 1. There are approximately 2,500 roof connections that have been successfully completed. The issues surrounding the incident on this connection are still being investigated and this will address whether in fact the work method statement was appropriately followed by the sub contractor in this instance.
During final inspection of drainage systems, defects were identified that are being rectified by the responsible sub-contractor as agreed with the consultant team. Multiplex has allowed for these works in its forecast programme. There are approximately 12 kilometres of drainage on the project. Approximately 25 discreet locations along the 12 kilometres are being rectified.
Please find attached additional information on the forecast completion sequence and site photographs.
Link to story :
[
www.multiplex.com.au]
Edited 2 time(s). Last edit at 2006-03-31 04:47 by Gazza.